Official EWA and Benayat route

EWA New Connection Bahrain: Electricity and Water Application Guide

By Gaurav Agarwal ยท Checked 6 October 2026

For a new EWA electricity or water connection to a property under construction, appoint a licensed engineering office to submit the request through Benayat. Prepare the ownership, permit, address, survey, identity and service-design documents, wait for EWA's design and quotation, pay the capital contribution, prepare the meter location and complete installation.

Who submitsEngineering office
Electricity time10 to 70 working days
Water time21 working days
FeeCalculated by EWA
Hand-painted house model beside an electric cable and teal water pipe
Original illustration for this EWA new-connection guide.
Jump to a step
  1. Choose the service
  2. Appoint an office
  3. Documents
  4. Electricity timing
  5. Water timing

01Choose new connection or open account

Use New Electricity Connection or New Water Connection when a property under construction needs new infrastructure, service lines or meters.

Official EWA New Electricity Connection Service page
The new-connection service is designed for construction and first supply.
Existing premise? If the service and meter already exist and you only need the account activated in your name, use EWA's Open Account or Open Account Reconnection service instead. Do not start a construction connection request for a normal tenancy move.

02Appoint a licensed engineering office

EWA instructs customers to submit both new electricity and new water applications through an engineering office using Benayat. The office coordinates the technical drawings, building-permit information and authority reviews.

  1. Choose an office from Benayat's licensed directory.
  2. Confirm whether you need electricity, water or both.
  3. Give the office the title, survey, address and building-permit records.
  4. Agree who will coordinate EWA comments and contractor corrections.
  5. Ask for the Benayat application reference.
Official Benayat Bahrain building-permit portal
New EWA connections for construction begin through the engineering-office and Benayat route.

For the complete building-permit sequence, use the Benayat Bahrain guide.

03Prepare the common connection documents

The official electricity checklist includes:

  • ID card or ID-reading data for citizens and residents, passport for non-residents, or CR or establishment certificate for commercial customers
  • electricity and meter services agreement
  • confirmed electricity supply load and details of required loads
  • building permit and address certificate
  • title deed, aerial map and survey certificate
  • tenant lease, registered lease and owner no-objection letter where applicable
Official EWA new electricity connection document checklist
The electricity request combines owner, property, permit and electrical-load records.

The water service uses the same core identity and property records, plus the Water Supply and Services Agreement. Follow the live checklist shown for the selected service because technical requirements differ.

Official EWA new water connection document checklist
The water checklist includes the supply agreement and property records.

04Understand electricity connection timing

EWA publishes different completion periods based on voltage and infrastructure:

Electricity situationPublished duration
Existing or partially completed infrastructure, low voltage10 working days
Existing or partially completed infrastructure, high voltage10 working days
New infrastructure, low voltage45 working days
New infrastructure, high voltage70 working days
Private-developer infrastructure, low voltage10 working days
Private-developer infrastructure, high voltage17 working days
Official EWA new electricity connection service durations
Electricity timing depends on voltage and whether infrastructure already exists.

These periods do not remove the time needed for complete drawings, external approvals, corrections, payment or site readiness.

05Follow the water connection sequence

EWA lists 21 working days for the new water connection service. The official steps are application and document review, site inspection, connection design and work permissions, fee calculation, quotation payment, site preparation, pipeline work and meter installation.

Official EWA New Water Connection Service page
Water connection is a separate technical service with its own agreement and inspection.
Official EWA new water connection duration
The current water-service page lists 21 working days.

06Pay the quotation and prepare the site

EWA does not publish one fixed connection price. Electricity charges depend on load and technical considerations, while water charges follow regulated pricing. EWA designs the connection and issues the quotation after the relevant approvals.

  1. Review the quotation and scope.
  2. Pay the capital contribution through an EWA payment channel.
  3. Keep the payment receipt with the application reference.
  4. Prepare the electricity meter box, water arrangement and access required by EWA.
  5. Have the licensed contractors complete corrections or inspection points.
  6. Confirm meter installation and service activation.

07Common connection delays

The application was submitted as Open Account

Ask whether the site already has active infrastructure and a meter. A new-build connection and an existing-premise account opening are different tasks.

The load details do not match the plans

Have the engineering office reconcile the load schedule, permit drawings and EWA confirmation before resubmission.

The quotation has not been issued

Check for missing external approvals, inspection comments or incomplete property documents in Benayat.

The meter cannot be installed

Confirm that the meter box, access and internal installations meet the requirements before requesting another visit.

You need EWA help

Call 17515555 with the Benayat and EWA reference numbers. EWA lists the contact centre as available 24 hours.

EWA new-connection questions

Do I need a new connection or an Open Account request?

Use a new-connection route when a property under construction needs new service infrastructure, lines or meters. If the premise already has the service and meter, use the appropriate Open Account or reconnection route.

Who submits a new electricity or water connection?

EWA instructs applicants to work through a licensed engineering office using Benayat. The office prepares and coordinates the technical submission, while the owner supplies the property, permit and identity records.

Is there a fixed EWA new-connection fee?

No single fixed price is published for every property. EWA designs the connection and calculates the quotation according to the load, infrastructure and technical work. Review the issued quotation before payment.

How long does a new electricity connection take?

EWA publishes periods from 10 to 70 working days depending on voltage and whether infrastructure already exists. Missing drawings, external approvals, corrections, payment or an unprepared site can add time outside that service estimate.

How long does a new water connection take?

The official water-connection page lists 21 working days. The sequence includes review, inspection, design, permissions, quotation, payment, site preparation, pipeline work and meter installation.

What details commonly delay the application?

Typical blocks are a mismatch between the load schedule and permit drawings, missing property or address records, incomplete external approvals and a meter location that is not ready for installation. Use the Benayat and EWA references when following up.